< Back
to Meeting Archives
Puget Sound Nearshore Partnership
Steering Committee Meeting
August 17, 2005
Attendees:
Curtis Tanner, Bernie Hargrave, Tim Smith, John Dohrmann,
Beth Coffey, Melissa Paulson, Elaine Kleckner, Dick Ecker,
Terry Wright, Debby Hyde, Paula Del Giudice, Jacques White,
Naki Stevens, Fred Goetz, Debbie Rick
Report from the Federal Project Manager
Lieutenant General Carl A. Strock, Commander and Chief of
Engineers, US Army Corps of Engineers, will not be able to
meet with the Partnership as planned. In lieu of that, Bernie
had scheduled Colonel Lewis and Colonel Martin to meet the
Nearshore Steering committee during lunch for a briefing on
the PSNERP General Investigation Study and the Nearshore Partnership,
and a site visit to adjacent Capitol Lake. Colonel Martin
and Colonel Lewis cancelled at the last minute.
Congressional Activities:
Congress has not enacted a Water Resources Development Act
(WRDA) since 2000. During that time, the Nation has engaged
in a healthy and constructive debate on the direction of water
resources policy and the values that should shape choices
in balancing environmental protection with economic growth.
The Corps of Engineers has implemented changes in its business
processes that capture the best of this debate. WRDA bills
in both the House and Senate address reasonable and balanced
approaches to these challenges.
Section 2019, HR 2864, the House-passed Water Resources Development
Act of 2005, would liberalize cost sharing of watershed assessments
by reducing the non-Federal share to 25 percent as originally
proposed by the office of Management and Budget in 2000. Sound
technical watershed assessments would support our ongoing
water resources management. The current higher 50 percent
rate of cost sharing makes watershed assessment more difficult
as incentives for local governments to cost share in a watershed
context are often restricted to projects of local interest
or governed by conflicts over water resources uses among multiple
political jurisdictions.
Comments: House version is more about Corps reform. This
bill has more interest on the East Coast. Allows maximization
of all available resources up to eight million dollars.
Question: Is WRDA the only way to a Construction General
(CG)?
Answer: Provides Nearshore construction authority and appropriation.
Bernie also reported on S.1224 A bill to protect the oceans,
and for other purposes.
SUMMARY:
National Oceans Protection Act of 2005 - Declares the purpose
of this Act is to secure for future U.S. generations a full
range of benefits of healthy marine ecosystems.
Bernie concluded his report by discussing emerging plans
for use of end of year funds. Priorities include:
1. The Nearshore Science Team could spend $8,000 - $12,000
for collaborative software that U of W would have to write
the Internet codes for. Several years ago the Corps purchased
from Microsoft a product called “Groove.”
Question to NST: Does Groove do what the NST needs it to
do?
2. Awarded $140,000 to CommEnSpace to validate the Nearshore
typology. They will advance the WRIA 9 change analyses and
develop classification rules for the nearshore types that
were not found in WRIA9.
3. Valued Ecosystem Components (VECs) white papers –
Will pay for as many of the white papers as possible with
current funds. Working on scope of work for Marine Riparian
white paper by Jim Brennan and Beach/bluffs paper by Jim
Johanassen. Any additional funds will be directed towards
Orca and great blue heron white papers.
4. Technical document editing and publication – Will
be completed by Washington SeaGrant and include the Conceptual
Model paper and the “Beach Dynamics Report”
written by David Finlayson.
5. Future without Project Conditions Analysis – Phase
1: Model Design. University of Washington research scientist
Marina Alberti will be contracted to develop a framework
for this task. $55,000
Off the Agenda Discussion - All
Jacques asked questions regarding the change analysis process.
Curtis reported that Si is developing a presentation that
should be available for the November Steering Committee meeting.
The need for improved coordination with Shared Strategy was
raised. The idea of a formal coordination meeting with Jim
Kramer and other staff of Shared Strategy was raised.
Tim – As Shared Strategy moves into implementation
phase, everyone will vote on what is most important to a healthy
Puget Sound – contaminants, landscape, storm water,
etc. The Nearshore Partnership needs to have conversations
about what PSNP is and is not doing. The Partners need to
understand, explain, and defend change analysis.
Jacques – He is getting mixed messages from the enviros.
The question is why waiting for PSNERP?
Tim – No one needs to wait for the NST to develop a
set of actions. Bill Hinesly, remarked that after a five year
General Investigation study Louisiana Coastal Areas has received
a 20 billion dollar implementation authority. Bill also said
the Nearshore Partnership was on a better trajectory.
All – discussed need for an outline of the project’s
general direction to use as a communications tool for the
upcoming Summit and other purposes.
Steering Committee Action:
Tim Smith, Debby Hyde, John Dohrmann, Jacques White to meet
to develop a nearshore process framework one-pager sometime
before the summit; for review by the Steering Committee at
the next meeting.
Implementation Team Co-Lead Report – Elaine
Kleckner and Beth Coffey
The Implementation Team is planning a joint meeting in October
with the Nearshore Science Team. Goals for that meeting are
to develop a “Strategic Needs” report outline
completed; Identify tasks to complete (who/what); have a non-specific
solutions map with a GIS initiative.
Interim Nearshore Projects Database Demonstration
– Elaine Kleckner
The database is in Microsoft Access 2000 and was developed
and is supported by IAC at no cost to the Nearshore Partnership.
The database currently resides on the WDFW server. It is currently
a single-user application with a PRISM-like architecture and
fields to ensure smooth transition to PRISM.
The interim Access database design and installation was completed
June 1 with project types, i.e., restoration, acquisition
(includes some protection projects), assessment, combinations
and project statuses, i.e., proposed, active, closed completed,
not completed. The database was populated with data inquiries
to Lead Entities and watershed planning groups, Marine Resources
Committees and tribes. Over 525 Project records have been
populated into the database, with more in progress; 100+ Organization
records entered and 100+ Person records entered. Follow-up
meetings to verify entries will be ongoing through August.
Elaine and Melissa continue to inquire to RFEGs, NGOs, others
for projects to enter. The Implementation Team has initiated
development of mapping capabilities.
Elaine then reported on discussions underway between WDFW
and IAC about PRISM migration issues, cost and timeline. Details
include:
- Currently PRISM is managed by IAC/SRFB, Washington state’s
consolidated recreation and conservation grant making agency.
IAC/SRFB manages 30 different state and federal grant programs
and uses PRISM to track over 6,000 projects.
- The Technical Stuff: PRISM has a client-server architecture
in Microsoft Windows. It requires a Microsoft SQL Database
Server, Microsoft Windows 2000 Server, Microsoft Visual
Basic 6.0.
- The benefits of PRISM are: it is a comprehensive project
management tool, online grant applications, contract management
and generation, provides accountability, integrated data,
reporting capabilities; mapping capabilities, and image
and document storage.
- PRISM Enhancements include: Monitoring Module for Salmon
Programs, Measurements/Metrics, Enhanced Attachment Module
(documents, photos, maps, other)
- Upcoming Enhancements include: Updated Architecture, Enhanced
Mapping Capabilities, Government Management, Accountability
and Performance, and Possible Expansion for Use by Other
Agencies.
- PRISM implementation steps would include performing a
comprehensive analysis to see if PRISM meets our needs (vision,
scope, requirements, constraints); Convene teams to design
modifications required to make the system fit our Project
Partnership; Define types and categories used for reporting;
work with other agencies and groups for consistency; Install
PRISM system. Set up lookup tables. Test; Prototype modifications,
have users do acceptance testing, continue working out design
details, have developers finalize modifications; Update
online help and other documentation, train staff; Convert
existing data to new system; Deploy to production environment.
Steering Committee Action:
Start developing an outline of management measures, potential
cost, and design. Incorporate a GIS into the Nearshore database.
Review with Corps personnel and Action Team.
Decision: Allocate $14,000 to migrating stand-alone database
into PRISM.
Capitol Lake Adaptive Management Plan (CLAMP)
presentation – Curtis Tanner
During recent State budget process, WDFW received $222,000
for the Deschutes Estuary Feasibility Study. Curtis has been
asked to by the Department to serve as the Project Manager.
As part of a $900,000 feasibility study, CLAMP is a good example
of an Early Action/ Demonstration Project. Early on, the “Guidance”
document was used to scope the feasibility study. Potential
benefits to PSNERP:
- Allows Nearshore Partnership to merge into an already
established project
- Opportunity to insure use and evaluate benefits of PSNERP
approach to restoration
- May provide opportunity to “bench test” use
of VECs in describing potential restoration project benefits.
Nearshore Science Team Co-Lead Report –
Fred Goetz
VEC White Paper Status
Of the nine “White Papers,” four have confirmed
authors, with recommendations out on the remainder.
- Megan Dethier, shellfish expert, Lead science writer
- Tom Mumford, eelgrass expert
- Kurt Fresh, Salmon in the Nearshore, dependant upon clearance
from NOAA that Kurt has the time and permission.
- Dan Pentilla, forage fish expert
The authors of the white papers need to have their work to
Megan no later than December; final product in March.
Presentation USGS Research -
At the July 2005 Nearshore Science Team meeting, Guy Gelfenbaum
(USGS) used the Lower Elwah River Dams removal and marine
area as a case study to illustrate the restoration implications
to adjacent nearshore ecosystems. Guy described the key components
of fish passage, marine-derived nutrients, fluvial restoration,
and sediment supply from the perspective of the on going and
anticipated USGS research activities. He also touched on the
research that other agencies (i.e., NOAA, tribes) are conducting.
The primary research questions driving the current USGS studies
described by Dr. Gelfenbaum relate to sediment transport to
nearshore ecosystems. A large amount of sediment is stored
in a relatively short system (from headwaters to release point)
behind the dams. The two primary sediment sources –
erosion within the reservoir and sediments coming down river
itself – are perceived to impose potential impacts as
well as restoration benefits to nearshore ecosystems. Based
on estimates by the Bureau of Reclamation (Randle, et al.)
sediments transported through system (three years and 50 years
intervals) from the erosion behind the dames are not expected
to be a high percentage and most erosion is predicted to occur
as a result of notching and hydrologic events.
Considerable work by the Tribe, NPS, and others, have concentrated
on historic change in the river channel and the delta that
could be interpreted as resulting from the dams effects on
sedimentation processes downstream and in the nearshore region.
The USGS (Coastal and Marine Geology Group) sediment studies
are focusing coastal mapping, process-based spatially explicit
morphological modeling, and process measurements. Coastal
mapping has illustrated seasonal changes in the delta, illustrating
40m progradation between summer and winter. Sonar and video
mapping of bottom substrates indicate extensive and complex
variation in sediment sizes and bedforms.
The process studies are linking nearshore current and salinity
dynamics to the observed changes in bathymetry and sediment
structure, and are using the DELFT3D model with sediment transport.
They are also examining the bathymetry of Ediz Hook, to evaluate
how much sediment that feeds Ediz Hook originates from river
discharge and delta as compared to bluff erosion.
This synthesis of on-going Elwah Dams removal studies illustrated
several issues about scientific assessment of demonstration
projects: Will the signal be big enough compared to natural
variability (in terms of sediment movement, beach morph, and
habitat)? May not be able to acquire accurate measures of
variability in only two-three years; may be multi-decadal
variation. And historic shoreline change “data”
is not much data at all and may not account for tidal changes,
season, etc.
Final comment based on this discussion of the NST’s
approach to learning about and formulating management (restoration/preservation)
measures is that, perhaps more than VECs, the PSNERP community
could use “white papers” on different management
measure to learn about restoration projects.
Status and Action Items
GI Feasibility Report
Fred Goetz led a discussion about purposes and organization
of USACE feasibility reports, using the Louisiana Coastal
Area (LCA) as an example. Important points of NST relevance
were: NST has most input 1) problem identification –
What are the causes of the problem? 2) Plan formulation –
What is it we need to do? What will we get out of it? What
are our scales? What are the VEC linkages, i.e., in terms
of “benefits”? 3) The NST conceptual model will
help justify or explain best available science for basic assumptions
behind.
A cost-benefit analysis will have to be an element of the
benefits analysis, but NST will have a role in determining
how this analysis is conducted especially from the perspective
of contingent and other indirect economic benefits. The NST
recognized that it needs to create 1) an organization process
map (“road map”) and 2) a geospatial map of restoration
needs and potential (alternative) solutions.
The end product of immediate need and utility is a “road
map” that describes organizational process to get to
a “non-specific solution map” (NSSM), that includes:
a) steps, linkages to get to viable solutions; b) identifies
what nearshore ecosystem processes are broken and where; and
c) provides generic solutions that are backed by quantified
objective for amount of change desirable (15% more sediment
delivery).
Future Without Project Conditions
The Future Without Project Conditions analysis is an extension
of trajectories from historic analysis that is framed by a
problem statement and is both a projection (from historic
trends) and a prediction (based on driving variables) of future
conditions if this project is not carried out. Fred Goetz
and Bill Hinesley (guest) described this analysis based on
the LCA feasibility report.
Dr. Marina Alberti, UW Urban Planning Professor, presented
some perspective on how her group would approach a Future
Without Project Conditions analysis based on a joint fact
finding approach. She described information sources and analyses
(i.e., Land Cover Change Model (LCCM) for Central Puget Sound)
that are being used presently to address similar sorts of
questions. Dr. Alberti and her colleagues are candidates for
PSNERP funding to assist in designing approach to Future Without
Conditions analyses.
WRIA9 Current Conditions and Change Analysis
For current conditions in WRIA 9, CommEnSpace will proceed
to a) complete WRIA9 historic conditions with inclusions of
missing data (e.g., upper Duwamish); b) develop rulesets that
cover shore types that were not included in WRIA9 (primary
candidate area is Whidbey Island Basin); and c) develop different
methodology for typing shoreline that will rely on better
data sets (higher resolution, bathymetry, etc.) to develop
typology, e.g., a data-driven, rather than interpretation,
effort.
Pacific Northwest Regional Collaboratory (PNWRC)
Coastal Applications Project
Establishing Land Use/Land Cover Linkages to the Nearshore
Environment for Restoration Planning in Puget Sound –
Dick Ecker
- Broad Focus Objective for PNWRC-PSRP Coastal Applications
project:
- Establish linkages between the terrestrial and aquatic
environments that will enhance or inform decisions regarding
prioritization of nearshore restoration sites using NASA
remote sensing products
- Develop project and products on a pilot scale that can
be scaled up to the greater Puget Sound region
Implemented Scope and Progress during Year 1: Efforts in
FY04 focused on developing a collaboration with the PSRP science
team and partnering with the City of Bainbridge Island jurisdiction
as a pilot study area to assess the long term planning and
restoration needs. A portion of this effort was spent determining
how best to support those needs with NASA remote sensing products
through the PNWRC. Specific tasks this past year included:
- Determining watershed drainage patterns to the nearshore
on Bainbridge Island (LiDAR and ArcHydro Hydrologic model)
- Developed impervious surface map for Bainbridge (Landsat
data)
- Determined percent impervious surface in stream buffers
and subwatersheds based on the hydrologic model and impervious
surface maps
Focus Effort for Year 2: Efforts in FY05 will expand upon
work conducted on Bainbridge Island in Year 1 and if funding
allows, be applied to a second Puget Sound site for validation.
Tasks this year will include:
- Determine if impervious surface maps/hydro basin delineations
improve the previously conducted Bainbridge Island nearshore
assessment ranking process for restoration
- Apply product information to selection of long term water
quality monitoring sites on Bainbridge Island (recently
funded WDOE project)
- Apply products to a second validation site (to be determined)
in Puget Sound if funding allows.
Existing Funding: $100K of funding from PNWRC was provided
in Year 1 (FY04). Approximately $85K of Year 2 funding is
available for this project.
Potential Future Funding: Similar funding level for the next
2-3 years is anticipated through the PNWRC. Funding for the
PNWRC is presently provided by NASA, and is considered “seed”
funding for this collaborative enterprise. The PNWRC intends
to maintain NASA funding, and also to obtain longer-term sustaining
funding from the end-user community that it serves.
Puget Sound Initiative Presentation –
John Dohrmann
Not much progress and Governor has been communicating to
her internal policy advisors.
Select Forum on Restoring Puget Sound: A Meeting
With National Experts – Naki Stevens
In September, the five sponsoring NGOs will host a two-day
Puget Sound Summit of 15 key local NGOs and 15 local tribal,
business, communications and political leaders, as well as
leaders from the Everglades, coastal Louisiana, and Great
Lakes ecosystem restoration projects.
On Day One, they will take visitors on a field trip to deepen
their understanding of the issues Puget Sound faces. On Day
Two, visitors will meet with the 30 summit participants and
will be asked to frame their remarks around two questions:
1. How did you elevate your ecosystem to one of national
significance in need of restoration and protection (i.e.
how did you market your ecosystem?)?
2. How can we organize ourselves to promote Puget Sound’s
status as a national treasure and gain significant new support
for Soundwide restoration?
Guest panelist speakers are:
Valsin Marmillion, President Sally Yozell,
Vice President
Marmillion + Company Battelle
Mark Davis, Executive Director Jeff Skelding,
Great Lakes Campaign Director
Coalition to Restore Coastal Louisiana National Wildlife Federation
Malia Hale, Director
National Wildlife Federation |