< Back
to Meeting Archives
Puget Sound Nearshore Partnership
Steering Committee Meeting
January 19, 2005
ATTENDEES:
Curtis Tanner, Paula Del Giudice, Jacques White, Debby Hyde,
Michael Rylko, Scott Redman, Rob Koeppen, Doug Osterman, Bernie
Hargrave, Tim Smith, Debbie Rick.
Bernie provided some edits to the December Notes. Notes approved.
Additional agenda items:
“State of the Sound”
NOAA partnership for demonstration/early action projects
Revise Shared Strategy Summit draft nearshore platform statement
Report from the Federal Project Manager –
Bernie Hargrave
Bernie reported that the FY ’05 allocation was $525,000
and that after “Savings and Slippage,” $418,000
would be available from the Corps. Bernie has bid on reprogramming
extra dollars toward early progress of the work plan; however
this has been unsuccessful.
The Nearshore Science Team has requested that the Steering
Committee hire a social scientist. This will be the topic
for discussion at the Project Management Team meeting on January
31.
The COE Plan Formulator (Beth Coffey) will be a member of
the Implementation Team. However, Beth is currently serving
in Iraq and will come on board after some vacation time. PSNERP
will have fifty percent of Beth’s time. Scott recommended
that Bernie Hargrave be the PSNERP’s representative
and lead on PSAW projects, and Beth Coffey be our PSNERP’s
representative and lead on the Corps’ General Investigation.
Tim Smith noted that after coming back from the Everglades
meeting, there is not a set approach for accomplishing General
Investigation Study Project Implementation Reports, Interim
Project Reports, Project Feasibility Reports, etc. We should
sit down and think about how we move from Stage III to project
implementation – there are many different paths. Everglades
is putting all their effort into the project feasibility studies
for specific projects.
Report from Nearshore Science Team Co-Lead –
Doug Myers
Doug Myers was not at the science team meeting, however he
reported that a staff graduate student will be hired to work
on the project.
There appears to be some confusion surrounding Early Action
Projects, Demonstration Projects and what the difference is
between these categories of projects The NST is working on
priority research questions that could be addressed through
Early Action and/or Demonstration projects.
Kurt Fresh will be at the next Steering Committee meeting
to present the NST’s preliminary list of priority of
research questions. These research questions are different
than the Research Plan, which describes broad areas of research.
Specific research questions developed by the NST may be included
as a “living” appendix to the Research Plan.
At the request of the federal project manager, NST meetings
have included discussions about future modeling needs. Preliminary
categories of modeling needs discussed have included:
- Project specific – e.g. Capitol Lake
- System level – e.g. PRISM
- Models to improve our understanding
System level nearshore model will have to be developed to
determine outcome of large-scale restoration actions
- NST has continued discussion of peer review. Initial needs
include review of three “in progress” technical
documents and is estimated to cost the program $3500 - $5000.
External peer review is suggested for the Research Plan,
Conceptual Model Narrative Report, and the Nearshore Typology.
A schedule for editing, review, and publication of these
documents has been developed. These documents will not be
complete in time for distribution at the Puget Sound/Georgia
Basin Research Conference, but will be complete June/July
of this year. The following Steering Committee members were
identified as points of contact to coordinate SC review
and comment of these documents, to be completed concurrently
with external peer review:
- Rob Koeppen – Research Plan Comments
- Michael Rylko – Conceptual Model
- Scott Redman - Typology
Progress on scoping Change Analysis was reported, including
a discussion of the use of a transition matrix approach to
document change.
An agenda item for future PMT was identified as the relevance/utility
of completed and on-going nearshore assessment efforts to
the PSNERP Work Plan. A Workgroup to follow up on this issue
was identified (Scott, Debby, Jacques, Curtis).
Regional Nearshore and Marine Chapter for the
Puget Sound Salmon Recovery Plan –
Scott Redman Scott reported that the Shared Strategy nearshore
summary is focused on the next ten years. Therefore, the focus
for restoration is on those actions that are both known to
be effective and possible in the near term. Our comments on
the draft platform statement were provided to Shared Strategy,
and resulted in somewhat stronger language supporting the
need for restoration of nearshore and marine ecosystems.
Comments from the Technical Review Team (TRT) to the Puget
Sound Action Team on the draft Regional Nearshore Recovery
Chapter included the need for a stronger link between hypotheses
and strategies, and specific actions, which result. They also
commented that the chapter was “juvenile Chinook-centric”
and did not sufficiently address Hood Canal summer chum needs/use.
Kurt Fresh will help the Puget Sound Action Team with revision
of the chapter.
Curtis commented that it was his opinion that one of the
key strengths of the PSAT draft chapter is that identifies
the fact nearshore serves regional needs, versus focus on
natal waters/river mouths inherent in the local chapters.
Executive Committee Meeting Debrief –
Tim Smith
Important Issues raised at the January 5, 2005 Executive
Committee Meeting.
- Branding
- EAP vs. Demonstration
- Valued Ecosystem Components
- Work Plan
- Funding Strategy
Update funding Strategy –
Tim Smith plans to meet with Brad Ack, Dan Evans, David Dicks
and Shared Strategy representatives to discuss next steps
in a more unified approach to funding requests. The big questions
that remains: How do we relate to each other?
There is s need for a caucus or coalition to provide “external”
support for Puget Sound restoration issues. Tim repeated earlier
suggestions that we also would benefit from a federal “caucus”
to highlight interagency cooperation. If PSNERP is indeed
going to be responsible for those elements of the Puget Sound
Action Team work plan relating to nearshore restoration, then
it follows that the Corps should be on the Puget Sound Action
Team; however Bernie reminded the PSNERP that for the Corps
to have membership on the Puget Sound Action Team requires
legislative action. Scott also said that US Geological Survey
should have ad hoc membership as they are contributing a good
portion to funding to play in the Nearshore.
The draft letter support endorsed by the Executive Committee
outlining the range of federal and state programs and agencies
that should be highlighted in support of nearshore issues
will be sent out to the Executive and Steering Commitees,
and the Nearshore Science Team members for their consideration.
The request is for each agency/organization to use the letter
as a template, modifying it as appropriate for their individual
interests and positions, then send to appropriate state and
federal legislators.
Work Plan – A schedule for revising the
PSNERP Work Plan was agreed upon:
- Review draft including updated task descriptions and timelines
sent to Steering Committee members for review and comment
at end of April.
- Discussion, review, endorsement at May Steering Committee
meeting.
- Revised draft to Executive Committee end of May
- Adoption by Executive Committee during June/July meeting
(TBD)
Deb Rick will begin to work with Executive Committee members
to schedule June/July meeting date.
Additional discussion regarding the Work Plan followed. There
needs to be discussion at the PMT level to determine what
an interim feasibility study would look like or be satisfactory
to meet the PSNERP’s need and satisfy the Corps criteria.
There needs to be a “Gut Check” about whether
we are where we think we are – what are the options
for how to get where we need to be.
The Work Plan needs to be laid out piece by piece on the
Gantt Chart showing the budget, funding level, resources available
and needed, etc. We are getting there as elements of the Work
Plan become trackable. Work Plan with budget showing good,
better, best scenario.
Phase II is articulated, however phase III is still very
abstract.
The need for additional Work Groups was discussed. Suggestions
included:
1) Implementation Team
2) How we relate to regulatory review/synthesis programs
– Agencies will meet and PSNERP will be invited to
share nearshore science.
3) Coalition building network of organizations outside
of local/federal government
4) Funding and grants finance committee (propose and compete)
5) Phase III strategy (Jacques White, Debby Hyde, Curtis
Tanner)
Tim advised that there is money coming PSNERP’s way
to complete Work Plan tasks, and we need to be responsive.
The meetings of the Steering Committees have become meetings
where the committee identifies tasks, but no one can do the
work.
Branding and Program Name – Curtis Tanner/Tim
Smith
The recommendation sent to the Executive Committee regarding
program logo and name was not endorsed.
Concerns raised by the Executive Committee included:
1. The Executive Committee suggested that the recommended
Program name (Puget Sound Restoration Program) was too broad,
therefore potentially promoting expectations that the scope
of the Program will address all issues contributing to degradation
of Puget Sound. We need to retain our focus on “nearshore.”
2. Concern that logo may resemble that of the Tulalip Tribes.
3. Need to adapt a Program tagline that is succinct and
expands appropriately upon the Program name to further describe
our identity.
After discussing these issues, the Steering Committee came
to the following conclusions:
1. The Steering Committee unanimously endorsed a suggested
Program name of Puget Sound Nearshore Partnership.
2. Adopted the original Orca artwork prepared for PSNERP
by James Madison as our Program logo.
3. After considerable discussion, the Steering Committee
settled upon “Restoring Our Ecosystem Health”
for the Program tagline. It is our feeling that each word
adds value to the Program identity, imparting a sense of
shared responsibility and urgency of mission.
These recommendations will be forwarded to the Executive
Committee for their endorsement.
Early Action and Demonstration Project Section
Language
Revised Work Plan language describing Early Action and Demonstration
projects, and their relationship to the program was reviewed
and discussed. Topics included:
- Under the revisions done to the Early Action and Demonstration
Project Section of the Work Plan, all Early Action projects
can also be Demonstration projects.
Is the primary purpose of a project to advance PSNERP, or
was it developed external to PSNERP?
Reformulate Implementation Team
The role and potential composition of the Implementation
Team was discussed. Suggested members included:
Michael Rylko
Scott Redman
Bernie Hargrave
Doug Myers
It was noted that the primary role of The Implementation
Team (IT) is not coalition building. The IT should develop
a list of project opportunities and identify potential projects
to inform the GI. The IT should also work on identification
of potential early action projects for inclusion in an interim
feasibility report.
News
Paul Cereghino has been looking for State Funds to match
NOAA restoration funds. On-going discussions with King County
and PSAT are occurring. He thinks that The total amount available
is around $200,000 - $300,000 (federal and match). |