< Back
to Meeting Archives
Puget Sound Nearshore Partnership Steering Committee
Meeting 18 July 2007
Attendance:
Andrea Copping, Dick Ecker, Bernie Hargrave, Debby Hyde,
Doug Osterman, Mike Ramsey, Tim Smith, Jennifer Steger, Hayden
Street, Curtis Tanner, Jacques White, Fred Goetz, Miriam Gilmer,
Toni Lick, Theresa Mitchell, Margen Carlson, Paul Cereghino,
and Debbie Rick
ESRP Final Funding Portfolio - Paul Cereghino
Paul presented a summary draft budget for the Estuary and
Salmon Restoration Program as follows:
| 2007 Appropriation |
|
$ 12,000,000 |
| Withheld for 2008 NOAA match |
|
$ (350,000)
$ 650,000 |
| Earmarked |
|
$ (3,746,875) |
|
|
Lower Dosewallips Floodplain |
|
|
| Carpenter Creek |
|
|
| Seahurst Park |
$ (1,100,000) |
|
| Duwamish Gardens |
|
|
| General Investigation |
|
$ (723,000) |
| Reserve |
|
$
(1,000,000)
$ 500,000 |
| Funds available for distribution
in 2007 |
|
$ (6,170,125)
$ 6,380,125 |
Notes for the above table:
- The function of the reserve would be to allow for changes
in project scope, leverage federal funds in FY 2008-9, and
funding of substantial projects in a 2008 RFP.
- The Implementation team divided up potential projects
for additional fact finding. A range of changes has occurred
over the course of investigation. Some uncertainties remain
to be resolved.
- TPL withdrew its $1M Green Point acquisition while providing
a commitment for $1M cash match for Pilot Point.
- WDFW has formally requested that USACE to participate
in Stilliguamish design under its existing general investigation
authority.
- A meeting with Nisqually Partners and WDFW discussion
resulted in preference for a $2 million funding level. The
goal was to assemble sufficient funds to initiate construction
in 2008 and leverage federal FY 2009 funds to complete dike
removal. A Second meeting is scheduled July 31 to better
frame collaborative funding strategy among partners.
- The NOAA Partnership Portfolio: $350 in NOAA funds would
be matched with $824k state match to fund 3 projects: Red
Salmon Slough Revegetation, Dungeness Estuary Tidal Reconnection,
Smugglers Slough Tidal Reconnection.
- Camp Kilworth should be skipped. They are holding a state
earmark sufficient for acquisition and are trying to raise
funds to transfer these resources to park improvements.
- Many minor changes are pending; many projects are anticipating
short-term budget refinements that will clarify appropriate
funding level.
Proposed portfolio.
Some savings could be found in cells highlight yellow pending
final budgets. Awards where there still is substantial uncertainty
are lit in orange
Click table to enlarge
The Steering Committee recommended that these points be made
regarding the summary table:
* Match be identified
* Total project cost
* Phase of Project
* Major funders
* Region
• Show all earmarked projects separately ~ “off
the top”
• Distinguish “hold back” $$ and “enhancement”
$$
• Show executive a full
project list (73) projects and their ranking.
• Jacques proposal is to hold back $650,000 for NOAA;
$500,000 for Enhancements; remainder on projects further
down list
• Draw line on table for funding limit
• Highlight rational for “pink” projects
for executives
• Consider “enhancements”
asterisk next to Hood Canal design
A future conversation should be “Current methods
don’t allow us to fund bulkhead removal.”
Resolve policy issue of poorly written grant applications.
Executive Committee Agenda – Tim Smith
1) Are we on the right trajectory to implement large-scale
restoration with the Corps and all other partners?
2) Is this the right time for this question? 6 months
~ a year
Project Manager’s Report #1
- Place for stakeholder involvement
- General approach to GI completion
- Introduce Anchor Environmental Project Manager for the
IDIQ
Project Manager’s Report #2
- Completion of GI
- How we implement from study to construction
- How we coordinate with other folks in Puget Sound
ESRP first?
Critical agenda elements
- ESRP Approval
- Clarity with executives RE: PSP and Nearshore’s
relationship to it
- Status of the GI (we have a path to and resources for
completion)
Future Discussion: Peer review of Nearshore’s
Science approach.
Contribution to Regional Programs
#1 How do we ensure the Nearshore’s process-based
restoration approach is endorsed by Puget Sound Partnership
(PSP)? We want this to happen because…
- Is implemented through various structures of PSP.
- Neashore scoping paper sets up our understanding of
our relationship to PSP
#2 Nearshore Partnership is bigger and broader than
a COE GI …How to utilize.
Do executives have advice about how to effectively discuss
#1 & #2
- Have executive presenters address questions about
Nearshore Partnership from perspective of their organization
- How can Nearshore Partnership support [PSP} regional
initiatives and vice versa?
- discussion leaders?
- Scoping pre-read frames conversation
After much discussion about the Executive Committee agenda,
the Steering Committee members asked Tim Smith to work it
out and have it sent electronically on Thursday, July 19.
Federal Project Manager - Bernie Hargrave
Bernie talked about a couple of agreements with WDFW that
the Corps has; 1) Stillaguamish, a design project, and 2)
Port Susan. Bernie gave the Woodward Bay – sediment
analysis as an example of a Section 22 agreement recently
signed with Washington Department of Natural Resources.
A Section 22 agreement allows a 50/50 cost-share between
the sponsor and Corps. The sponsor's portion can be provided
as 50% in-kind services and 50% cash; or some lesser portion
of in-kind and greater portion cash. Money flows backwards
to the federal grant cycles, that is, away from the state
and to the feds. There are two other proposals to WDFW for
a Marine Resources Committees and a Restoration Manual.
The following News Release was not sent as a
read-ahead.
Senator Murray Secures Millions in Funding to Help Washington
State Water Projects
Funding will go to habitat restoration, flood control, erosion
mitigation, dredging and dam reconstruction - For Immediate
Release: Tuesday, June 26, 2007 - (Washington, D.C.) –
Today, U.S. Senator Patty Murray (D-WA) included millions
in funding for Washington state waterways in an annual Senate
spending bill. The funding will be used on habitat restoration,
flood control, erosion mitigation, dredging and dam reconstruction
projects. The funding was unveiled in the Senate Energy
and Water Appropriations bill. Senator Murray is a senior
member of the Energy and Water Subcommittee.
"These funds will help restore species' habitats,
protect communities from flooding, dredge economically vital
waterways, and improve the overall health and vitality of
our state's waterways," said Senator Murray. "I
am proud to support the vital work that the Army Corp of
Engineers and local communities are undertaking to keep
our environment clean, our citizens safe, and our economy
moving. I am committed to protecting and preserving our
state's water resources."
Washington state projects slated to receive
funding include:
Elliot Bay Seawall Study- $750,000
This funding will go toward a study to document the problems
and opportunities associated with the seawall and formulate
potential plans for a solution. The 70-year-old Alaskan
Way Seawall is failing and needs to be replaced. Tiny marine
organisms, known as gribbles, are attacking and significantly
weakening the wood timbers that make up the structural support
of the seawall.
Puget Sound Nearshore – $1.5 million
These funds will support identification, design and construction
of the best habitat restoration sites in the areas along
the bank of the Puget Sound.
Walla Walla Watershed Restoration - $100,000
This funding will go toward addressing water supply and
fish habitat issues in the Walla Walla Watershed. This project
is supported by environmental, tribal, farming, and irrigation
interests as well as The National Marine Fisheries Service,
U.S. Fish and Wildlife Service, and Natural Resource Conservation
Service. The Walla Walla Watershed includes three main river
systems the Walla Walla, Touchet, and Mill Creek.
Lake Washington Ship Canal Restoration - $400,000
These funds will support habitat and ecosystem restoration
efforts in the Lake Washington Ship Canal watershed. This
is critical to the region’s environmental and economic
future.
Centralia Flood Control – $150,000
These funds will go toward finding a solution to flooding
in the Chehalis River basin.
These funds will continue critical efforts to design and
construct a flood control project that would help to stop
closure of Interstate 5 during flood season.
Shoalwater Bay Shoreline - $1.5 million
These funds will fund a critical erosion protection project
near Willapa Bay. Currently, shoreline erosion is progressing
at an alarming rate at the Shoalwater Tribe’s reservation.
This loss includes tidal areas that include shellfish beds,
which provide a major portion of the tribe’s livelihood.
The project Murray is funding will go toward a barrier to
help mitigate the effects of erosion.
Lower Columbia River Ecosystem Restoration
- $1.5 million
This funding will provide habitat restoration in the Lower
Columbia River. This will benefit endangered salmon, steelhead,
and various other species.
Mud Mountain Dam Construction – $15.3
million
These funds will be used to replace the 100-year old diversion
dam on the White River near Seattle and will enable the
Corps to meet ongoing fish passage needs. It will also be
used for operations of the current facility.
Mt. St. Helens Sediment Control - $10.2 million
These funds will be used to continue to control sediment
flows in the Cowlitz and Toutle Rivers. In February, Senator
Murray visited this project to receive a status briefing
from the Army Corp of Engineers. Murray also held a community
roundtable to discuss the project with local residents.
Swinomish Channel Dredging - $500,000
This funding will be used to dredge Swinomish Channel in
Northwest Washington. The Swinomish Channel needs to be
dredged every three to four years to prevent groundings.
The channel is used for commercial and recreation purposes
including: boat builders, log-tow companies, fishermen,
dry boat operators and boaters. The channel needs to be
dredged to a depth of 12 feet.
Murray Provides $700,000 in Funding for Skagit
River Flood Control Study
For Immediate Release: Tuesday, June 26, 2007
(Washington, D.C.) – Today, U.S. Senator Patty Murray
(D-WA) announced that she has included $700,000 in funding
for an Army Corp of Engineers study on Skagit River flooding
in an annual Senate spending bill. The Corp study is looking
at the best way to proceed with a flood control plan in
the region. The funding was included in the Senate Energy
and Water Appropriations bill. Senator Murray is a senior
member of the Energy and Water Subcommittee.
"The Washington state residents who live in the Skagit
River floodplain deserve a long term solution to the flooding
problems along the river," said Senator Murray. "These
funds will be used to identify problems, and generate potential
solutions that will reduce the chance of a flood catastrophe."
The funding Murray has provided will be used to support
the Skagit General Investigation Study which is examining
the flooding problems of the Skagit River. Risk of flooding
in the Skagit basin is the largest on the West Coast.
The Skagit River floodplain includes the cities of Mount
Vernon, Burlington, and Sedro-Woolley. Mount Vernon and
Burlington are currently protected by levees that are inadequate
for the large floods that have occurred in the past and
are predicted to recur. Catastrophic levee failure would
result in a huge economic disaster and potential loss of
human life. According to the Corps’ Economic Baseline
Report, damage estimates to Burlington and Mount Vernon
are over $1.9 billion for a large flood.
A significant Skagit River flood would also close critical
Washington state transportation routes including Interstate
5, State Highway 20, and the BNSF Railroad. This would result
in limiting emergency response and would have a damaging
economic impact.
Senator Murray Provides $5 Million in Funding
for Water Restoration Projects in Puget Sound and Green and
Duwamish Rivers
$3 million to restore Puget Sound and Adjacent
Waters; $2 million for Green and Duwamish River Restoration
For Immediate Release: Tuesday, June 26, 2007
(Washington D.C.) – Today, U.S. Senator Patty Murray
(D-WA) announced that she has included $5 million in funding
for water restoration projects in Western Washington. The
funding will go toward projects in the Puget Sound and Green
and Duwamish Rivers. The funding was included in the Senate
Energy and Water Appropriations bill. Senator Murray is
a senior member of the Energy and Water Subcommittee.
The projects Murray secured funding for will be performed
by the Army Corp of Engineers. The President did not include
any funding for either of these critical Washington state
projects in his 2008 budget request.
Green and Duwamish River Ecosystem Restoration
- $2 million
This funding will go toward river basin restoration that
is supported by King County, the cities of Kent, Tukwilla,
Covington, Renton, and numerous other cities and communities.
The Green/Duwamish basin has experienced vast changes due
to urbanization of the lower watershed, filling of the estuary,
construction of dams, and heavy industrial and residential
development in the area. Natural habitats for fish and wildlife
have been destroyed. This restoration project is a comprehensive
program for the entire Green/Duwamish ecosystem from the
tidal estuaries to the spawning and wildlife habitat areas
in the upper basin.
“This funding will improve our environment, assist
in the recovery of endangered salmon, and advance the economic
interests of the area," said Senator Murray. "I
am glad that I have been able to support the efforts of
King County and the many communities along these rivers
who are committed to restoration efforts."
Puget Sound and Adjacent Waters - $3 million
These funds will continue a habitat restoration program
throughout the Puget Sound basin. The goal of the Puget
Sound and Adjacent Waters Restoration Program is to recover
ecosystem processes and habitats that have been altered
or destroyed through development within the basin. To achieve
this goal, projects will be prioritized based on criteria
developed in consultation with tribal governments, Federal,
state, and local agencies and stakeholders.
"It is so important that we invest in counteracting
the environmental impacts that industrialization and urbanization
have had on state treasures like the Puget Sound,"
said Senator Murray. "These funds will go toward restoring
the habitats of many vital species in the Puget Sound basin."
Nearshore Science Team - Fred Goetz
Sub Basin Map
The NST submitted PSNERP recommended delineations as follows
– “This map is an adaptation of nine oceanographic
basins originally identified by the Puget Sound Ambient
Monitoring Program. The adaptations include the combination
of the east and West Straits of Juan de Fuca sub basins
into a single Strait of Juan de Fuca sub basin; the combination
of the Georgia Strait and San Juan Archipelago sub basins
into a single San Juan Islands sub basin; the extension
of the southeast boundary of the San Juan basin following
the sill that extends from near the southwest portion of
Lopez Island to near Point Partridge on Whidbey Island to
better represent the influence of the Fraser River; the
extension of the southern boundary of Admiralty Inlet (North
Central Puget Sound) to a line from Point No Point on the
Kitsap Peninsula to near Possession Point on the southern
end of Whidbey Island to better address the Triple Junction,
and; the extension of the Hood Canal sub basin to include
all waters south of Tala point and Foulweather Bluff per
RCW90.88.005(4) that identifies this as the Hood Canal Rehabilitation
Zone and serves as the framework for programs directed at
the recovery of Hood Canal. Upland regions of each area
were delineated based on freshwater drainages with slight
adjustments to boundaries between marine basins to match
littoral drift processes.”
Action Items from the Wall Notes:
- Steering Committee endorsement of map? Send to PSP as
a recommendation
- E-copies of map to steering committee members
- Thank you to NST
- Send Map and accompanying materials to PSP and federal
caucus under JPK’s letterhead ~ point out consistency
among us as a value
NST Peer-Review Recommendation to PMT
Si Simenstad resubmitted for consideration a recommendation
to identify NST desire for a formal peer review process
to be submitted to Project Management Team and Executive
Committee. The NST is in full agreement about the need
for a peer review process, including a programmatic review
panel/committee; and, for peer review to be effective it
needs to be implemented early enough in the process that
the results can still affect constructive change in GI,
and not just a rubber stamp. The most pressing needs for
peer review are to evaluate PSNERP science strategy and
direction, and programmatic structure. Si will try to condense
recommendation into 2-pg document in time for PMT/SC/EC
review this summer.
Draft
NST Perspective on PSNERP Peer Review attached.
Action Items from Wall Notes
- Steering Committee comments on proposed methodology to
Bernie & Curtis by 8/06
- Note DOE review process is distinct from NST proposal
- Action Item Next Steering Committee - Any action related
to peer review proposal?
Reformulation of Change Analysis/SNAR Workgroups
Change analysis needs to start to develop/morph into SNAR,
but there is some concern about a full transition from CA
into SNAR, CA group still has some unfinished business (e.g.,
EAU, CA work plan needs to address data gaps such as 700
miles of shoreline without armoring data).
Some tasks should be ready for contractor (Anchor Environmental)
to move ahead with; Jen Burke will act as liaison. The other
activities will need closer inspection by the NST. It was
suggested that we maintain a merged SNAR workgroup, with
a CA (subcommittee) component. This should help to structure
contractor’s work and provide opportunities to check-in.
Monthly meetings at a minimum. Anchor’s main role
will be CA, Anchor can observe meetings and assist with
SNAR as process moves along.
Formulating Goals and Objectives
Based on the Retreat, Jacques, Doug, and Tom M. would form
a group to define how goals and objectives will be defined,
used, etc. First task is to draft a scoping paper. Goals
and Objectives might be more defined by social preferences
as opposed to scientific/ecological preferences. There is
not a technical answer to ‘how much restoration needs
to be done?’ Instead ask question ‘how much
restoration needs to be done in order to (fill-in the blank)?’
NST has not been clear to-date on establishing processes
as goals and this is how to measure them. Restoration of
processes is not the ultimate goal; it is the means to an
end, the end being a social value. But, NST needs to be
explicit on why objectives can not be framed in quantitative
terms, if this is the case.
New Shoreline Armoring Workgroup (SAW)
Guy Gelfenbaum has drafted prospectus for group. It is
proposed that this be an interdisciplinary team of coastal
scientists to review existing science on coastal ecosystem
processes related to shoreline armoring in Puget Sound (much
information exists on open coasts, but not protected waters).
Before moving much further, need resolution on budgets,
NST recommendations, and PMT support. PMT supports idea,
but needs specifics before writing checks. There was some
concerned expressed that resources might be taken away from
GI to work on armoring studies; conversely, there was some
anticipation that the USGS should fund this study. Si has
given approval to proceed as planned until final decisions
come from PMT or SC.
Implementation Team - Miriam Gilmer / Doug Myers
In addition to what was reported by Fred Goetz in the NST
report, the Implementation Team is looking at the methods
that Si put together for the SNAR and reconfiguring the
first two chapters. First review will be August 1, with
the Crops Team review in mid-August.
The PM’s have asked the IT to apply Corps plan formulation
process to the ESRP criteria and ranking data. We hope to
evolve ESRP more toward what is expected from early actions
of the future large-scale construction authority and to
better formulate future large-scale projects from what we
learn through ESRP.
Mike Ramsey reported that the Recreation and Conservation
Office (IAC) received $40.75 million for Habitat Restoration.
The legislation states that Nearshore/Estuary projects be
coordinated/approved by the Puget Sound Nearshore Partnership.
Action Item: List of projects from RCO for review,
coordination, approval.
Next Meeting: August 15, 2007
@ Olympia, Attorney General’s Office at Capitol Court
1.0 hours Project Managers, NST, and IT Reports
1.5 hour Executive Committee De-Brief
1.5 hours Presentation on the Habitat Work Schedule by Erik
Neatherlin
1.0 hour Any action related to peer review proposal?
.5 hour List of projects from RCO for review, coordination,
approval
.5 hour Puget Sound Partnership Update (if any)
|